Maintenance of MEG system
Checks to be made
Helium level
Every two days, check the helium level: it should be higher than 50%
Check the gas flow and pressure of the ATP and the ATL
If the helium pressure is low (Low G FLOW on the ATL):
Remove the hose between the ATP and the ATL
Check whether helium is passing through the hose
Plug the hose in again and see whether G Flow increases
Restart the ATL using the green button on the rear panel
Air pressure
Check the air pressure every month.
The air pressure must be around 0.7 to 0.8; if it is not, this could indicate a compressor problem
When the air pressure is low, the MSR door can get stuck
Compressor working hours
The working hours of the ATL and ATP compressors are shown on the small display of each compressor. This is the number of hours the compressor has been in operation.
MSR door
Test the emergency button every week
Check whether releasing the pressure with the emergency button is getting harder, or whether the pressure is not released as it should be
If you use the manual handle, put the handle back in its original position afterwards; otherwise the door will not reset
Data retrieval from ATP and ATL for diagnostic
When the ATP and ATL helium recovery system exhibits a low gas flow or an unusual temperature or pressure, contact the people listed in the contacts table below and provide them with the diagnostic data of both devices.
The detailed retrieval steps, including IP addresses and credentials, are kept in the internal version of this page.
Helium refill process
Bijoy (bs4233@nyu.edu) indicates that helium tanks are needed and communicates this need to Neelima Dinil (nd1508@nyu.edu)
Hadi receives an email asking him to approve the request for helium tanks
Hadi confirms the request by replying, with Osama, Bijoy, Neelima and Nyavili Miyanda (vili.mulemba@nyu.edu) in copy
Neelima schedules the delivery of the tanks with Bijoy
Bijoy schedules the helium refill as necessary
When a new PO is needed to cover the dewar costs, issue one using the CTP Requisition form, then inform Jinna
The ATL tank (QD recovery system) is used to refill the dewar. However, when the tanks inside the ATL room are full, some helium needs to be evacuated into the lab so that the ATL tank starts to fill again when it is placed back into the recovery system.
System |
Refill date |
Helium level Before |
Helium level after |
Nominal range |
|---|---|---|---|---|
ATL Compressor |
x/y/z |
0 |
0 |
0 |
Request for new equipment/IT or Helium Dewar
CTP members can raise requests to purchase new equipment, lab supplies and so on.
Helium refill: schedule and monitoring
A refill is needed when the helium level meter behind the dewar indicates a level below 20%. The level should not go below 20%: when it starts approaching 20%, a refill is needed
Bijoy comes to check the measurement physically, on the display
Every Monday, Bijoy and his team perform the helium refill
The team comes at 9 am UAE time on Monday
If the level falls below 20% before the next Monday, a refill takes place before that Monday
The team takes the following measurements and logs them in the Excel sheet:
the helium level at the dewar
the ATL level (L Volume on the display)
the output pressure of the AT recovery compressor
the ATP input and output pressures
the cylinder levels
the gas counting meter at the back of the helium room
the chilled water temperature (there are two thermostats)
Every 3 months, the water filter is replaced
Everyone wears cryogenic gloves during the maintenance intervention
Helium refill: notes from the lab
The notes below were taken while observing a refill from the ATL; the formal procedure is given in the next section. Filling from an external helium dewar provided by a supplier follows a slightly different procedure.
Shut down the ATL system from its touch screen: Mode, then Stop. After 10 seconds it stops, and the ATL compressor is off as well
Remove the right and left pipes from the back of the ATL, as well as the electric power plug and the gas pipe (4 connections in total)
Move the red ATL cylinder to the back of the dewar
Take the needle (transfer line). When the needle is put into the ATL cylinder, a flash, a little noise and some fog occur
Check the T diode value on the ATL (a built-in battery keeps the display of the ATL powered on). If it is above 3, some helium must first be evacuated using the second valve. When it is below 3, proceed with the needle
Before refilling, turn the Apollo handle 90 degrees counter-clockwise, to the transfer position
If the pressure is high, some gas is released at this point from the valve near the Apollo handle. When the pressure is very high, the valve can be partially closed for a few minutes to avoid a strong evacuation of the high pressure. Once the pressure is gone, open the valve fully again (red handle pointing south)
Remove the cap at the back of the dewar
Insert the short end of the needle into the port of the dewar from which the cap was removed, then tighten it
Put the ATL in transfer mode
Press the green square Start button on the Automatic Helium Supplier device
Wait a few minutes: the level shown on the Automatic Helium Supplier should start increasing. During this time, the liquid helium is transferred to the dewar, while the vapor is channelled through the tubes back to the 4 cylinders
When the 4 cylinders are full (the gauge pressure shows 70; unit to be checked), the light turns red. If more liquid helium is needed while the cylinders are full, some vapor must be released using the black handle above the KIT racks; keep it open until the filling is finished
The filling stops when either the cylinders are full or the helium level has reached 90-95%. The filling should also be stopped if the ATL is below 20 litres
To stop the filling, set the ATL to stop the transfer, then press “Stop” (the red square button) on the Automatic Helium Supplier
Disconnect the needle from the dewar side and from the ATL side, and put it back in its place
Move the ATL system back to the helium chamber and connect it again. Before restarting the ATL, put the yellow handle back to BPC
Turn the ATL on, in liquefaction mode
Make sure that the black handle above the rack is properly closed and that the cap at the back of the dewar is back in place
Update the Excel sheet with the new helium values
Helium refill: step-by-step procedure
Before the helium refill, record the following data in the logbook:
amount of liquid helium in the MEG, in %
gas counter
medium pressure (MP) hub screen: outlet P
ATP screen: volume of purified gas, pressure (P) input, P output
ATL screen: L volume
Stop the ATL by pressing MODE → STOP → OK
Disconnect the gas inlet, supply, return and electrical connector from the rear side of the ATL. Release the wheel brake if necessary
Switch the yellow valve handle to the TRANSFER position (horizontal)
Move the ATL to the MEG room
Press the green START button on the MEG level meter
Put on protective face shields and adequate cryo-gloves
Release and remove the plug from the transfer port, and carefully insert the transfer line into the port. Do not bend the transfer line! It must remain vertical at all times. Stop inserting when the thick portion of the transfer line passes through the sealing washer, then tighten the washer
Slowly lower the transfer line until a white plume comes out of the other side
Insert this side into the MEG inlet port, and seal the port by tightening the washer if necessary
Slowly lower the transfer line into the ATL until it touches the bottom, then pull it back by 3-5 cm
Start the refill by pressing MODE → TRANSFER → 5. Press CANCEL if compressor activation is requested. Touch the screen again to return to the main menu
Observe the change of the helium level in the ATL (decreasing) and in the MEG (increasing)
Terminate the refill when one or more of the following conditions are fulfilled:
the ATL helium level is below 10 L
the MEG helium level is above 90%
the red overfill light on the wall is activated
Lift the transfer line by 60-70 cm. Wait approximately 30 seconds and unplug the line from the MEG port. Then quickly remove the transfer line from the ATL
Press the red STOP button on the MEG level meter and the green POWER button on the wall box of the MEG
Move the ATL back into the soundproof enclosure and activate the wheel brake
Switch the yellow valve handle to the BPC position (vertical)
Connect the gas inlet, supply, return and electrical connector at the rear side of the ATL
Start the ATL by pressing MODE → LIQUEFY → SLOW
Record in the logbook the same data as in the first step. The procedure is then complete
Important
If the difference between P input and P output on the ATP screen is 4 PSI or higher, make sure that the medium pressure (MP) hub outlet pressure is below 5 bar, then start the ATP regeneration by pressing MODE → REGENERATION → LOW TEMPERATURE REGENERATION → OK.
Contacts table
Name |
Number |
Role |
|
|---|---|---|---|
Hadi Zaatiti |
+971 56 275 4921 |
Research Scientist |
|
Lawrence Torres |
NA |
NA |
|
Qiang Zhang |
NA |
NA |
|
QD Helium Recovery |
NA |
NA |
|
QD Konstantin Voigt |
NA |
NA |
|
QD Tobias Adler |
NA |
NA |
|
Ahmed Ansari |
NA |
Helium store manager (Primary contact for getting Helium tanks) |
|
Mohammad Rakib |
NA |
Logistics and Sanitation Coordinator |